Massive new overbridge reaches halfway point to transform key route near Solihull
By Emily Griffin 19th Nov 2026
Construction of a new HS2 road bridge over the A45 near Bickenhill has reached the halfway stage, ahead of further traffic changes coming into force next month.
The Coventry Road overbridge is being built to allow high-speed trains to travel beneath the A45, between Stonebridge Island and Junction 6 of the M42.
Over the past 11 months, engineers working for HS2 construction partner Balfour Beatty VINCI (BBV) have completed the first half of the structure.
The bridge is being built in two sections to maintain existing traffic flows along the A45 and minimise disruption to the local road network.
Using a 'top down' construction method, around 7,500 tonnes of earth has been excavated from beneath the existing carriageway.
Waterproofing and highway works are expected to be completed in the coming weeks, allowing the eastbound section of the new bridge to open.
From Monday, December 7, a series of overnight and weekend road closures will be introduced to allow traffic to switch onto the new bridge.
HS2 said access to businesses and properties would be maintained during the temporary closures and urged motorists to familiarise themselves with diversion routes.
Paul Marshall, head of delivery at HS2 Ltd, said: "Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway.
"During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we'll ensure that access to businesses and properties is maintained."
Work on the second half of the bridge is due to begin in the new year, following a similar construction process.
Richard Husbands, project manager at BBV, said reaching the halfway point was an important milestone.
He said: "The Coventry Road overbridge is one of the key crossings on this part of the route, allowing the railway to pass under the A45 as it approaches Interchange Station.
"Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project."
Construction above ground is expected to continue throughout 2027, with the bridge structurally complete by the end of that year.
Permanent highway works, including the installation of lighting, kerbs and drainage, will then take place in liaison with National Highways.
The completed bridge and final road alignment are expected to be in use by summer 2028.